Open Hours: Mn – Fri, 9:00 a.m. – 6:00 p.m

Project Timeline

14 Feb 2022
Concreting of DPC
Concreting of Damp Proof Course at Building 6
28 Jan 2022
Wall Screeding
Wall Screeding at Building 1 underway
04 Dec 2021
Blinding of Foundation Trenches
Blinding of Foundation Trenches at building 6 and 7
21 Nov 2021
Removal of Roof Slab Formwork
Removal of Roof Slab Formwork at Building 2
27 Oct 2021
Building Plastering
Plastering of Building 1 and 2
8 Sep 2021
Ready-mix Concrete Casting for TV1-TV4
Ready-mix Concrete Casting

 

Ongoing work for the ready-mix concrete Casting of Roof beams, slabs and gutters for Twin Villas 1-4 and second floor slab form work goes up for Twin Villa 17-20.

6 Aug 2021
Form-work for roof slabs and gutters
Form-work for roof slabs and gutters

Work progresses on the form-work for roof slabs to safely support the reinforced concrete until it has reached adequate strength for the building. Also, new excavated trenches for upcoming Twin Villa Foundations.

15 Jun 2021
2nd floor slab form construction
2nd floor slab form construction for Twin Villas 1-4

 

Second floor slab form work goes up for Twin Villa (TV) 1,2,3 and 4. Basement retention and floors commencing for Twin Villas 17, and 18.

5 May 2021
1st floors of the first two Twin Villas
1st floors of the first two Twin Villas Constructed

Service plumbing’s and reinforcements for the first two Twin Villas are being connected while building foundations for Twin Villa 17|18 approaches completion as you can see the ongoing casting of ready-mix reinforced concrete slabs.

8 April 2021
DPC, Foundation Block Wall & Underground Cabling
DPC, Foundation Block Wall & Underground Cabling

Moisture control has been applied to building walls and floors to prevent moisture from passing into the interior spaces. As further foundation block walls are prepared, underground cables are installed. 

5 Mar 2021
Blockwork for foundation commences
Blockwork for foundation

Concrete block foundation has been installed for the first unit in order to support the weight of the building as trenchwork for the next unit begins simultaneously. 

10 Feb 2021
Excavated Building Trenches
Excavated Building Trenches

With completed culvert achieved, site prepared; an ecofriendly structure is set for development. Our maiden sample unit foundation is prepared.

5 Jan 2021
Diversion of Stream
Diversion of Stream

We rerouted an existing water body that previously cut across the site to restrict flows and combat the effects of erosion on the site.

14 Dec 2020
Coffer Dam Installation
Coffer Dam Installation

The reinforced concrete culvert is installed to allow water flow away from our site in a channeled structure.

6 Nov 2020
Site Preparation
Site Preparation

Our first task of site preparation was the clearing site, leaving it in a graded condition which involved the removal of trees, removing all old underground infrastructure, and any other obstacles that might affect the construction process.

Site Progress Gallery