Open Hours: Mn – Fri, 9:00 a.m. – 6:00 p.m

Our Projects

    By using this form you agree with the storage and handling of your data by this website.

    6 Nov 2020
    Site Preparation
    Site Preparation

    Our first task of site preparation was the clearing site, leaving it in a graded condition which involved the removal of trees, removing all old underground infrastructure, and any other obstacles that might affect the construction process.

    14 Dec 2020
    Coffer Dam Installation
    Coffer Dam Installation

    The reinforced concrete culvert is installed to allow water flow away from our site in a channeled structure.

    5 Jan 2021
    Diversion of Stream
    Diversion of Stream

    We rerouted an existing water body that previously cut across the site to restrict flows and combat the effects of erosion on the site.

    10 Feb 2021
    Excavated Building Trenches
    Excavated Building Trenches

    With completed culvert achieved, site prepared; an ecofriendly structure is set for development. Our maiden sample unit foundation is prepared.

    5 Mar 2021
    Blockwork for foundation commences
    Blockwork for foundation

    Concrete block foundation has been installed for the first unit in order to support the weight of the building as trenchwork for the next unit begins simultaneously. 

    8 April 2021
    DPC, Foundation Block Wall & Underground Cabling
    DPC, Foundation Block Wall & Underground Cabling

    Moisture control has been applied to building walls and floors to prevent moisture from passing into the interior spaces. As further foundation block walls are prepared, underground cables are installed. 

    5 May 2021
    1st floors of the first two Twin Villas
    1st floors of the first two Twin Villas Constructed

    Service plumbing’s and reinforcements for the first two Twin Villas are being connected while building foundations for Twin Villa 17|18 approaches completion as you can see the ongoing casting of ready-mix reinforced concrete slabs.

    15 Jun 2021
    2nd floor slab form construction
    2nd floor slab form construction for Twin Villas 1-4

     

    Second floor slab form work goes up for Twin Villa (TV) 1,2,3 and 4. Basement retention and floors commencing for Twin Villas 17, and 18.

    6 Aug 2021
    Form-work for roof slabs and gutters
    Form-work for roof slabs and gutters

    Work progresses on the form-work for roof slabs to safely support the reinforced concrete until it has reached adequate strength for the building. Also, new excavated trenches for upcoming Twin Villa Foundations.

    8 Sep 2021
    Ready-mix Concrete Casting for TV1-TV4
    Ready-mix Concrete Casting

     

    Ongoing work for the ready-mix concrete Casting of Roof beams, slabs and gutters for Twin Villas 1-4 and second floor slab form work goes up for Twin Villa 17-20.

    27 Oct 2021
    Building Plastering
    Plastering of Building 1 and 2
    21 Nov 2021
    Removal of Roof Slab Formwork
    Removal of Roof Slab Formwork at Building 2
    04 Dec 2021
    Blinding of Foundation Trenches
    Blinding of Foundation Trenches at building 6 and 7
    28 Jan 2022
    Wall Screeding
    Wall Screeding at Building 1 underway
    14 Feb 2022
    Concreting of DPC
    Concreting of Damp Proof Course at Building 6